Site Preparation Checklist for EX4400 Switches
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for EX4400 switch installation.
Item or Task |
For More Information |
Performed by |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances. |
Environmental Requirements and Specifications for EX4400 Switches |
||
Power | |||
Measure the distance between external power sources and the switch installation site. |
Clearance Requirements for Hardware Maintenance for EX4400 Switches |
||
Locate sites to connect system grounding. |
|||
Calculate the power consumption and requirements. |
|||
Hardware Configuration | |||
Choose the number and types of switches you want to install. |
|||
Rack or Cabinet | |||
Verify that the rack or cabinet meets the minimum requirements for installing the switch. |
|||
Plan rack or cabinet location, including required space clearances. |
|||
Secure the rack or cabinet to the floor and building structure. |
|||
Cables | |||
Acquire cables and connectors:
Note:
The Ethernet cables to connect to the RJ-45 network ports on EX4400-24P, EX4400-24MP, EX4400-48P, and EX4400-48MP switches provide 90-W power over 4-pair wire. To ensure that the cables do not exceed the rated temperature and ampacity and to ensure proper operation, the cables must meet the following specifications related to deployment, temperature rise, category, IEEE, UL, NEC, and local electric codes:
|
|||
Plan the cable routing and management. |