QFX10008 Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a QFX10008 chassis installation.
✓ |
Item or Task |
For More Information |
---|---|---|
Environment | ||
□ |
Verify that environmental factors such as temperature a humidity do not exceed router tolerances. |
|
Power | ||
□ |
Measure the distance between external power sources and the router installation site. |
|
□ |
Calculate the power consumption and requirements. |
|
Rack | ||
□ |
Verify that your rack meets the minimum requirements for the installation of the router. |
|
□ |
Plan rack location, including required space clearances. |
QFX10000 Clearance Requirements for Airflow and Hardware Maintenance |
□ |
Secure the rack to the floor and building structure. |
|
Cables | ||
□ |
Acquire cables and connectors:
|
The list of supported transceivers for the QFX10008 line cards is located at https://pathfinder.juniper.net/hct/product/#prd=QFX10008. |
□ |
Plan the cable routing and management. |
|
□ |
Hardware Upgrades | Order individual components. See QFX10008 Configurations and Upgrade Options. |