Site Preparation Checklist for the SRX1500 Firewall
Table 1 provides a checklist of tasks you need to perform when preparing a site for installing the SRX1500 Firewall.
Item or Task |
Additional Information |
Performed By |
Date |
Notes |
---|---|---|---|---|
Power |
||||
Measure distance between external power sources and device installation site. |
||||
Locate sites for connection of system grounding. |
||||
Calculate the power consumption and requirements. |
SRX1500 Services Gateway AC Power Supply Electrical Specifications and SRX1500 Services Gateway DC Power Supply Electrical Specifications |
|||
Environment |
||||
Verify that environmental factors such as temperature and humidity do not exceed device tolerances. |
||||
Rack Installation |
||||
Verify that your rack meets the minimum requirements. |
||||
Plan rack location, including required space clearances. |
||||
If a rack is used, secure the rack to the floor and building structure. |
||||
Cabinet Installation |
||||
Verify that your cabinet meets the minimum requirements. |
||||
Plan the cabinet location, including required space clearances. |
||||
Cables |
||||
Acquire cables and connectors. |
SRX1500 Services Gateway Supported AC Power Cords and SRX1500 Services Gateway DC Power Cable Specifications |
|||
Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected. |
||||
Plan the cable routing and management. |