Site Preparation Checklist for the JRR200 Route Reflector
Table 1 provides a checklist of tasks you need to perform when preparing a site for installing the JRR200 Route Reflector.
Item or Task |
Additional Information |
Performed By |
Date |
Notes |
---|---|---|---|---|
Power |
||||
Measure distance between external power sources and device installation site. |
||||
Locate sites for connection of system grounding. |
||||
Calculate the power consumption and requirements. |
||||
Environment |
||||
Verify that environmental factors such as temperature and humidity do not exceed device tolerances. |
||||
Rack or Cabinet |
||||
Verify that your rack or cabinet meets the minimum requirements for the installation of the device. |
||||
Plan rack location, including required space clearances. |
||||
Secure the rack or cabinet to the floor and building structure. |
||||
Cables |
||||
Acquire cables and connectors:
|
||||
Plan the cable routing and management. |