QFX10002 Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a QFX10002 installation.
Item or Task |
For More Information |
Performed By |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances. |
|
|
|
Power | |||
Measure the distance between external power sources and the switch installation site. |
|
|
|
Calculate the power consumption and requirements. |
|
|
|
Rack | |||
Verify that your rack meets the minimum requirements for the installation of the switch. |
|
|
|
Plan rack location, including required space clearances. |
QFX10002 Clearance Requirements for Airflow and Hardware Maintenance |
|
|
Secure the rack to the floor and building structure. |
|
|
|
Cables | |||
Acquire cables and connectors:
|
|
|
|
Plan the cable routing and management. |
|
|
|