Site Preparation Checklist for ACX1000 and ACX1100 Routers
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for ACX1000 and ACX1100 router installation.
Item or Task |
For More Information |
Performed By |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed router tolerances. |
|||
Power | |||
Measure the distance between external power sources and router installation site. |
|||
Locate sites for connection of system grounding. |
|||
Calculate the power consumption and requirements. |
|||
Hardware Configuration | |||
Choose the number and types of routers you want to install. |
|||
Rack or Cabinet | |||
Verify that your rack or cabinet meets the minimum requirements for the installation of the router. |
|||
Plan rack or cabinet location, including required space clearances. |
Clearance Requirements for Airflow and Hardware Maintenance on ACX1000 and ACX1100 Routers |
||
Secure the rack or cabinet to the floor and building structure. |
|||
Cables | |||
Acquire cables and connectors:
|
|||
Plan the cable routing and management. |