MX204 Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you must perform when preparing a site for router installation.
Item or Task |
For More Information |
Performed by |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed router tolerances. |
|||
Power | |||
Locate sites for connection of system grounding. |
|||
Measure distance between external power sources and router installation site. |
|||
Calculate the power consumption and requirements. |
|||
Rack | |||
Select the type of rack or cabinet. |
|||
Plan rack or cabinet location, including required space clearances. |
MX204 Router Clearance Requirements for Airflow and Hardware Maintenance |
||
If a rack is used, secure rack to floor and building structure. |
|||
Cables | |||
Acquire cables and connectors:
|
Calculating Power Budget and Power Margin for Fiber-Optic Cables |