Help us improve your experience.

Let us know what you think.

Do you have time for a two-minute survey?

header-navigation
keyboard_arrow_up
close
keyboard_arrow_left
SRX345 Firewall Hardware Guide
Table of Contents Expand all
list Table of Contents
file_download PDF
{ "lLangCode": "en", "lName": "English", "lCountryCode": "us", "transcode": "en_US" }
English
keyboard_arrow_right

SRX345 Site Preparation Checklist

date_range 27-May-23

Table 1 provides a checklist of tasks you need to perform when preparing a site for installing the SRX345 Firewall.

Table 1: Site Preparation Checklist for SRX345 Firewall Installation

Item or Task

Additional Information

Environment

Verify that environmental factors such as temperature and humidity do not exceed device tolerances.

SRX345 Services Gateway Environmental Specifications

Power

Measure the distance between the external power sources and the device installation site.

SRX345 Services Gateway Electrical Wiring Guidelines

Locate sites for connection of system grounding.

Connecting the SRX345 Services Gateway Grounding Cable

Calculate the power consumption and requirements.

SRX345 Services Gateway Power Specifications and Requirements

Rack Requirements

Verify that your rack meets the minimum requirements.

Rack Requirements

Rack Installation

Plan the rack location, including required space clearances.

Preparing the SRX345 Services Gateway for Rack-Mount Installation

Secure the rack to the floor and building structure.

 

Cabinet Requirements

 

Verify that your cabinet meets the minimum requirements.

Cabinet Requirements

Plan the cabinet location, including required space clearances.

 

Cables

 
  • Acquire cables and connectors.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

  • Plan the cable routing and management.

footer-navigation