QFX5110 Site Preparation Checklist

date_range 09-Mar-21

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a QFX5110 installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed By

Date

Architecture

Determine whether the QFX5110 device will operate:

  • standalone

  • as a member in a Virtual Chassis

  • as a spine or leaf in a Virtual Chassis Fabric (VCF)

 

 

Environment

Verify that environmental factors such as temperature and humidity do not exceed switch tolerances.

QFX5110 Environmental Requirements and Specifications

 

 

Power

Measure the distance between external power sources and switch installation site.

 

 

 

Calculate the power consumption and requirements.

QFX5110 AC Power Specifications and QFX5110 DC Power Specifications

 

 

Rack

Verify that your rack meets the minimum requirements for the installation of the switch.

QFX5110 Rack Requirements

 

 

Plan rack location, including required space clearances.

QFX5110 Clearance Requirements for Airflow and Hardware Maintenance

 

 

Secure the rack or cabinet to the floor and building structure.

 

 

 

Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

QFX5110 Network Cable and Transceiver Planning

 

 

Plan the cable routing and management.

 

 

 