PTX10003 Site Preparation Checklist

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a PTX10003 installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed by

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed router tolerances.

PTX10003 Environmental Requirements and Specifications

 

 

Power

Measure the distance between external power sources and the router installation site.

 

 

 

Calculate the power consumption and requirements.

 

 

Rack

Verify that your rack meets the minimum requirements for the installation of the router.

PTX10003 Rack Requirements

 

 

Plan rack location, including required space clearances.

PTX10003 Clearance Requirements for Airflow and Hardware Maintenance

 

 

Secure the rack to the floor and building structure.

 

 

 

Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

See the Hardware Compatibility Tool.

 

 

Plan the cable routing and management.