- play_arrow Fast Track: Initial Installation
- play_arrow Overview
- play_arrow Initial Installation and Configuration
- play_arrow Maintaining Components
- play_arrow Troubleshooting Hardware
- play_arrow Contacting Customer Support and Returning the Chassis or Components
- play_arrow Safety and Compliance Information
- General Safety Guidelines and Warnings
- Definitions of Safety Warning Levels
- Qualified Personnel Warning
- Warning Statement for Norway and Sweden
- Fire Safety Requirements
- Installation Instructions Warning
- Chassis and Component Lifting Guidelines
- Restricted Access Warning
- Ramp Warning
- Rack-Mounting and Cabinet-Mounting Warnings
- Grounded Equipment Warning
- Laser and LED Safety Guidelines and Warnings
- Radiation from Open Port Apertures Warning
- Maintenance and Operational Safety Guidelines and Warnings
- General Electrical Safety Guidelines and Warnings
- Action to Take After an Electrical Accident
- Prevention of Electrostatic Discharge Damage
- AC Power Electrical Safety Guidelines
- AC Power Disconnection Warning
- DC Power Electrical Safety Guidelines
- DC Power Copper Conductors Warning
- DC Power Disconnection Warning
- DC Power Grounding Requirements and Warning
- DC Power Wiring Sequence Warning
- DC Power Wiring Terminations Warning
- Multiple Power Supplies Disconnection Warning
- TN Power Warning
- PTX10003 Regulatory Standard Compliances
PTX10003 Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a PTX10003 installation.
Item or Task | For More Information | Performed by | Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed router tolerances. |
|
| |
Power | |||
Measure the distance between external power sources and the router installation site. |
|
|
|
Calculate the power consumption and requirements. |
|
| |
Rack | |||
Verify that your rack meets the minimum requirements for the installation of the router. |
|
| |
Plan rack location, including required space clearances. | PTX10003 Clearance Requirements for Airflow and Hardware Maintenance |
|
|
Secure the rack to the floor and building structure. |
|
|
|
Cables | |||
Acquire cables and connectors:
| See the Hardware Compatibility Tool. |
|
|
Plan the cable routing and management. |
|
|
|