- play_arrow Fast Track: Initial Installation
- play_arrow Overview
- play_arrow Initial Installation and Configuration
- play_arrow Maintaining Components
- play_arrow Troubleshooting Hardware
- play_arrow Contacting Customer Support and Returning the Chassis or Components
- play_arrow Safety and Compliance Information
QFX5130 Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a QFX5130 installation.
Item or Task | For More Information | Performed by | Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances. |
|
| |
Power | |||
Measure the distance between external power sources and the switch installation site. | — |
|
|
Calculate the power consumption and requirements. |
|
| |
Rack or Cabinet | |||
Verify that your rack or cabinet meets the minimum requirements for the installation of the switch. |
|
| |
Plan the rack or cabinet location, including the required space clearances. | QFX5130 Clearance Requirements for Airflow and Hardware Maintenance |
|
|
Secure the rack or cabinet to the floor and building structure. | — |
|
|
Cables | |||
Acquire cables and connectors:
|
|
| |
Plan the cable routing and management. | — |
|
|