The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a QFX5130 installation.
Item or Task |
For More Information |
Performed by |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances. |
|
|
|
Power | |||
Measure the distance between external power sources and the switch installation site. |
— |
|
|
Calculate the power consumption and requirements. |
|
|
|
Rack or Cabinet | |||
Verify that your rack or cabinet meets the minimum requirements for the installation of the switch. |
|
|
|
Plan the rack or cabinet location, including the required space clearances. |
QFX5130 Clearance Requirements for Airflow and Hardware Maintenance |
|
|
Secure the rack or cabinet to the floor and building structure. |
— |
|
|
Cables | |||
Acquire cables and connectors:
|
|
|
|
Plan the cable routing and management. |
— |
|
|