Overview of Preparing the Site for the PTX5000
To prepare a site for PTX5000 installation:
- Verify that environmental factors such as temperature and humidity do not exceed PTX5000 tolerances.
- Verify that the site and installation plan meets all safety guidelines and requirements.
- Locate sites for connection of system grounding.
- Calculate the power consumption and requirements.
Measure the distance between external power sources and the PTX5000 installation site.
For an AC-powered PTX5000
See PTX5000 Three-Phase Delta AC Power Distribution Unit Specifications
See PTX5000 Three-Phase Wye AC Power Distribution Unit Specifications
For a DC-powered PTX5000:
- Plan rack location, including required space clearances.
- Verify that the plan for power installation meets all electrical safety guidelines.
- Verify that your rack meets the minimum requirements for the installation of the PTX5000.
- Plan to secure the rack to the floor and building structure.
- Acquire cables and connectors:
Determine the number of cables and type of cable needed based on your planned configuration.
The PTX Series Interface Module Reference describes the PICs supported on PTX Series routers.
- Tip:
You can use the Hardware Compatibility Tool to find information about the pluggable transceivers supported on your Juniper Networks device.
Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.
- Plan the cable routing and management.